The work has been delayed – it seems they finished someone else’s pool back in March and it promptly collapsed into an underground hole they had not detected. It’s taken them a month to dig it all out and start over, whislt trying not to fall TOO far behind on any one else’s pool – result, everyone’s a little delayed. But the structure is in place now, the concrete is booked for Monday, and we’re assured that once the concrete has set, there’s only four to six days work involved in the lining and plumbing, filling in the rest of the hole, and finishing off the tiles, etc. Oh well, it’s all good clean fun.